Malaysia
13 cited records · 13 accepted observations · 0 pending review
19 cited research updates · context only
- Malaysia Data Centre Task Force / Ministry of Digital · 27 DCTF-approved data-centre projects · status through July 2026DCTF-APPROVED COHORT · STATUS THROUGH JUL 2026 · 1 REPORTED OPERATING / 26 UNDER CONSTRUCTION · NO MW DISCLOSED
Malaysia’s DCTF cohort: 27 approved projects, with one reported operating by July 2026
Malaysia · DCTF-approved cohort across Johor, Selangor and Negeri Sembilan · Published 15 Oct 2026
Secondary reporting of a Ministry written reply; the underlying parliamentary answer and project-level register were not independently retrieved. The direct The Star article is dated 15 October 2026; the linked Bernama report is dated 14 October 2026 and is the same reporting lineage rather than independent corroboration. The one-operating/26-under-construction split applies only to the 27-project DCTF cohort and must not be presented as a nationwide operating share. The RM225.97bn is estimated project investment, not verified spend, committed data-centre capex, operating value or available capacity. Project count and employment are reported expected/status figures; no project MW, IT-load basis, firm power, grid connection, tenant, commissioning date or site-level operating status is supplied. Excluded from operating-capacity totals and scores.The Star report of a Digital Ministry written parliamentary reply source ↗ - Government of Malaysia / TNB / Energy Commission / DOSM · Monthly electricity consumption and supply datasets · H1 2025 versus H1 2026OBSERVED OFFICIAL MONTHLY SERIES · JAN 2018–JUN 2026 · H1 2026 PROVISIONAL · NATIONAL SCOPE · NOT FIRM POWER
Malaysia H1 electricity use rose 6.1%; broad commercial load rose 6.9%
Malaysia · national electricity system · Published 08 Oct 2026
National, multi-sector context—not data-centre consumption, Johor or Peninsular load, firm MW, reserve margin, connection availability, curtailment, tariff economics or site headroom. The commercial category includes industrial and mining demand and cannot be attributed to data centres. H1 totals are calculated by summing the six published monthly MKWh observations and dividing by 1,000; percentages use unrounded source values. The latest six months are provisional and may be revised. Identical supply and consumption totals must not be subtracted to manufacture a headroom figure. Excluded from operating-capacity totals and scores.Government of Malaysia data.gov.my source ↗ - DC Byte · Global Index Report 2026 · APAC Future Growth Metro MarketsDC BYTE 2026 APAC FUTURE-GROWTH RANK · KUALA LUMPUR #1 · JOHOR #9 · CONTEXT ONLY
Kuala Lumpur leads DC Byte's 2026 APAC future-growth list, with Johor ninth
Kuala Lumpur (including Cyberjaya) and Johor · Published 05 Aug 2026
This is a proprietary, point-in-time ordinal ranking—not an NTRY score, a capacity value, available headroom, an operating-capacity total, a forecast or a repeated series. It is regional to APAC and is methodologically separate from DC Byte's current-market index, where Johor ranks first and Kuala Lumpur eighth; the two lists must not be merged into one score. Two future-growth inputs include under-construction and committed capacity, neither of which is guaranteed to become operational. The report does not publish the Malaysian metros' component values or Growth Potential Scores, and the rank distance between first and ninth does not measure a capacity or investment-attractiveness gap. Excluded from operating-capacity totals and scores.DC Byte source ↗ - DC Byte · The Hyperscale Build RaceDC BYTE REPORT PUBLISHED 26 NOV 2025 · APAC REGIONAL CONTEXT · NOT ACCEPTED CAPACITY
APAC hyperscale capacity grew at a 32.9% five-year CAGR as pre-leasing stretched 24–36 months
APAC regional context · Malaysia named as an emerging hub · Published 26 Nov 2025
The 32.9% figure is a DC Byte regional aggregate, not a Malaysia growth rate, and the public landing page does not disclose the exact five-year endpoints or calculation table. The 24–36-month range is an industry pattern, not a contractual rule for every campus. The delivery-model chart is a point-in-time 2024 snapshot built from proprietary intelligence; its underlying numeric table and lifecycle scope are not published on the landing page, so no MW values, market shares or operating-capacity totals are transcribed or inferred. This context does not change governed market coverage, an NTRY score or accepted capacity. Excluded from operating-capacity totals and scores.DC Byte source ↗ - TM Nxera / Telekom Malaysia / Tenaga Nasional · TM Nxera Iskandar Puteri campus280 MW SUPPLY AGREEMENT · FIRST BUILDING TOPPED OUT · H2 2026 OPERATIONS TARGET · NOT VERIFIED LIVE
TM Nxera tops out its first Johor building—but 280 MW contracted power is not yet delivered capacity
Iskandar Puteri, Johor · Published 16 Apr 2026
The 280 MW figure is company-reported contracted electricity-supply scope, not proof of energized, delivered, available or operating power. The more-than-200 MW figure is campus scalability, not live IT load; the two scopes are different and must not be added or converted into utilization. Topping-out is a construction milestone, while customer onboarding and a commercial-operations target do not prove occupancy, service commencement or revenue. PUE of no more than 1.30 and renewable-energy integration are design aims, not measured performance. Excluded from operating-capacity totals and scores.Telekom Malaysia source ↗ - Bitdeer AI · A901 AI Cloud Campus10-YEAR FACILITY SERVICES AGREEMENT · INITIAL DELIVERY Q1 2027 · FULL 67 MW Q2 2027 · NO OFFTAKE · NOT OPERATING
Bitdeer secures a 67 MW Malaysia AI campus for 2027—but A901 has no customer offtake yet
Malaysia · city not disclosed · Published 08 Oct 2026
This is a company-reported facility-services agreement and future delivery target, not an operating facility or an end-customer offtake commitment. Bitdeer states that no A901 offtake commitments had been entered into as of 8 October 2026. The company's active AI Cloud pipeline above US$10 billion is management's estimate of aggregate potential contract value under commercial discussion; it is not backlog, revenue, an executed contract or a binding commitment. All capacity figures are critical IT load. The Tech Capital reported the announcement on 13 October 2026. Excluded from operating-capacity totals and scores.Bitdeer Technologies Group source ↗ - Bitdeer AI · A103 Malaysia Data Center8-YEAR FACILITY AGREEMENT · Q1 2028 ENERGISATION TARGET · NO OFFTAKE · NOT OPERATING
Bitdeer secures a 60 MW A103 facility agreement in Cyberjaya—but no customer offtake yet
Cyberjaya · Published 12 Oct 2026
All figures are company-reported critical IT load and describe nested or overlapping scopes that must not be added. 'Secured' means owned capacity or capacity under an executed data-center services agreement; it does not mean constructed, energized, commissioned, operating, available or customer-contracted capacity. Bitdeer states that no A103 offtake commitments existed as of 12 October 2026. The 71.5 MW campus scope includes A103 alongside A101 and A102; the 333.5 MW portfolio spans Malaysia, Norway and the United States; and 350 MW is a global ceiling target. The more-than-US$10 billion active pipeline is a management estimate, not backlog, revenue, an executed contract or a binding commitment. Excluded from operating-capacity totals and scores.Bitdeer Technologies Group source ↗ - SPAN / Malaysia water service operators · Six largest published state/territory rowsOFFICIAL 2024 STATE COMPARISON · TOP SIX PUBLISHED ROWS · PROVISIONAL · NOT DATA-CENTRE WATER USE
Selangor accounted for 31.3% of Malaysia's provisional 2024 non-domestic water consumption
Malaysia · Published 30 Sept 2026
Point-in-time 2024 comparison of broad non-domestic customer accounts, not a trend and not data-centre water use. The chart shows the six largest published state/territory rows rather than the complete national distribution. Selangor includes W.P. Kuala Lumpur and W.P. Putrajaya, so it is not a standalone state-only value. Consumption is not water-system capacity, allocation, entitlement, drought resilience, potable or non-potable supply, cooling-water availability or campus deliverability. The source marks 2024 as provisional and subject to revision. CC BY 4.0. Excluded from operating-capacity totals and scores.Government of Malaysia / National Water Services Commission source ↗ - SPAN / Malaysia water service operators · JohorOFFICIAL 2019–2024 JOHOR NON-DOMESTIC SERIES · 2024 PROVISIONAL · NOT DATA-CENTRE WATER USE
Johor non-domestic water consumption reached 610 MLD in 2024—but the category is broader than data centres
Malaysia · Published 30 Sept 2026
Johor annual non-domestic customer-account context only. The category includes all non-domestic accounts and does not isolate data centres, hyperscalers, industrial parks or cooling demand. It is consumption, not water-system capacity, allocation, entitlement, drought resilience, potable or non-potable supply, cooling-water availability or campus deliverability. The source marks the most recent year, 2024, as provisional and subject to revision. CC BY 4.0. Excluded from operating-capacity totals and scores.Government of Malaysia / National Water Services Commission source ↗ - Malaysia electricity system · National all-sector electricity consumptionOFFICIAL MONTHLY GRID SERIES · JUNE COMPARISON · 2026 PROVISIONAL · NOT DATA-CENTRE-SPECIFIC
Malaysia's June electricity consumption is 28.5% above 2020—but data-centre demand is not isolated
Malaysia · Published 08 Oct 2026
This is an all-sector national consumption series, not data-centre electricity use, peak demand, available generation, grid headroom or deliverable power. The dataset does not isolate data centres from commercial, industrial, mining or domestic load, and its latest six months are provisional and may be revised. The sequence therefore cannot establish causation, size the data-centre supply-demand gap or enter operating-capacity totals. Excluded from operating-capacity totals and scores.OpenDOSM / data.gov.my source ↗ - Equinix · KL2 CyberjayaPLANNED FACILITY · FULL BUILD-OUT BASIS · COMMISSIONING DATE UNDISCLOSED
Equinix plans a US$190m-plus KL2 expansion with more than 2,200 cabinets
Kuala Lumpur · Published 12 May 2026
KL2 is planned, not operating. The release gives no commissioning date, delivered power, IT-load MW, occupancy, customer commitments or utilisation. Cabinet count is not comparable with MW, and the US$190m-plus figure is announced investment rather than verified spend. The renewable-energy statement is a day-one coverage target, not operating evidence. Excluded from operating-capacity totals and scores.Equinix source ↗ - NEXTDC · KL1 Kuala LumpurOFFICIAL LAUNCH · CUSTOMER UTILISATION UNDISCLOSED
NEXTDC launches KL1 as its first international data centre
Kuala Lumpur · Published 14 May 2026
The operator's launch statement does not disclose occupied IT load, customer utilisation or delivered-power evidence. Tier IV design requirements are not the same as independently certified operating performance. Excluded from operating-capacity totals and scores.NEXTDC source ↗ - Digital Realty · Malaysia platformMARKET PLATFORM ESTABLISHED · CAPACITY EFFECT UNVERIFIED
Digital Realty establishes its Malaysia operating platform in Cyberjaya
Cyberjaya · Published 08 Jun 2026
Market entry and platform establishment do not by themselves prove new delivered capacity, occupancy or utilisation. Any MW claims require a separate scope-matched source and lifecycle check. Excluded from operating-capacity totals and scores.Digital Realty source ↗ - Malaysian Investment Development Authority · Data Centre Nexus 2026GOVERNMENT POLICY SIGNAL · NO PROJECT CAPACITY CLAIM
MIDA shifts Malaysia's test from attracted capacity to local capability
Malaysia · Published 14 Sept 2026
The investment figure is a multi-year national aggregate, not verified spend, delivered capacity or operating capacity. MIDA's demand outlook is not a committed project pipeline. Excluded from operating-capacity totals and scores.Malaysian Investment Development Authority source ↗ - Bitdeer AI · A201 Malaysia Data CenterOFF-TAKE COMMITTED · Q1 2027 ENERGISATION TARGET · NOT OPERATING
Bitdeer contracts more than 70% of A201 before its planned energisation
Johor Bahru · Published 29 Sept 2026
A201 is not yet energised. The approximately 21.7 MW figure is planned site capacity, while more than 70% is a company-reported commitment floor—not an exact contracted-load value. Applying that floor to the rounded site capacity implies more than approximately 15.2 MW; this is transparent NTRY arithmetic, not a separately source-reported measurement. The uncommitted remainder is not evidence of available or deliverable capacity. Expected revenue, delivery timing, customer performance, equipment deployment and power availability remain forward-looking. Excluded from operating-capacity totals and scores.Bitdeer Technologies Group source ↗ - Bitdeer AI · A102100% OFF-TAKE COMMITTED · Q1 2027 SERVICE TARGET · NOT ENERGISED OR OPERATING
Bitdeer moved A102 from approximately 50% to 100% contracted in twelve days
Johor · Published 31 Aug 2026
This is a two-disclosure company-reported commitment-coverage sequence, not observed customer load, utilisation, energised capacity, operating capacity, delivered power or a facility SLA. The 19 August value was stated as approximately 50%, while the 31 August release said A102 was sold out; the chart must not be used to infer a precise daily contracting rate. The 9.5 MW is planned site capacity, and revenue, service timing, customer performance, customer prepayments and delivery remain forward-looking. Excluded from operating-capacity totals and scores.Bitdeer Technologies Group source ↗ - Key ASIC / CT Vision · Proposed Green AI Data Centre complex · site not disclosedNON-BINDING MOU · DEFINITIVE AGREEMENTS TARGET Q4 2026 · SITE UNDISCLOSED · NOT OPERATING
Key ASIC and CT Vision sign a non-binding MoU targeting about 300 MW of IT load
Malaysia · Published 04 Sept 2026
This is a preliminary, non-binding MoU-stage target with no named site or commercial-launch date. The approximately 300 MW figure is planned IT load—not delivered or contracted power, grid draw, renewable generation, firm supply, constructed, commissioned or operating capacity—and receives zero operating-capacity credit. The renewable-energy and PUE figures are targets, not measured performance. Definitive agreements have not been executed; feasibility, site, grid connection, regulatory approvals, financing, construction, energisation, commissioning, customers and operating evidence remain unverified. Excluded from operating-capacity totals and scores.Key ASIC source ↗ - G3nerasi Kinta · Proposed Perak hybrid solar PV and four-hour BESS projectTERM SHEET ENTERED 28 SEP 2026 · DEVELOPMENT STAGE · 2029 CONDITIONAL COD · NOT OPERATING
G3nerasi Kinta signs a term sheet for a proposed 680 MWac solar PV and four-hour BESS project
Perak · Published 29 Sept 2026
This is a term sheet and the project remains at development stage. The 680 MWac is minimum net renewable-generation capacity—not data-centre IT load, contracted grid headroom, average delivered power, firm capacity or operating capacity. The filing discloses four-hour BESS duration but not its MW or MWh size. The offtaker is unnamed; definitive BESC and CRESS agreements remain unexecuted; and the 2029 COD depends on a Renewable Energy Supply Access Agreement with TNB and required CRESS approvals. SD Guthrie separately describes an up-to-1.2 GW solar-assets partnership target, but the sources do not establish a common capacity basis or confirm that the 680 MWac counts toward it, so no ratio, residual or additive total is shown. Excluded from operating-capacity totals and scores.SD Guthrie / Bursa Malaysia source ↗ - Ministry of Energy Transition and Water Transformation / Parliament of Malaysia · Written parliamentary reply · approved supply and 2030 maximum-demand projection12.3 GW APPROVED SUPPLY ENVELOPE · AS OF AUG 2026 · 8.39 GW 2030 MAX-DEMAND PROJECTION · NOT OPERATING LOAD OR GRID HEADROOM
Malaysia had approved 12.3 GW of data-centre electricity supply by August—but projected 2030 maximum demand was 8.39 GW
Malaysia · national data-centre electricity approvals · Published 20 Oct 2026
Secondary reporting of a written parliamentary reply; the underlying answer and project-level approval register were not independently retrieved. The 12.3 GW is approved electricity-supply capacity for projects as of August 2026—not operating IT load, actual grid draw, delivered power, generation capacity, reserve margin or campus-ready headroom. The 8.39 GW is projected sector maximum demand for 2030—not a contracted load, floor or observed peak. The two figures have different lifecycle meanings and must not be subtracted to claim 3.91 GW of spare capacity. No project list, utility, region, voltage, connection date, energisation status, commissioning status or cancellation risk is published in the report. Policy safeguards and a 30% renewable-energy requirement do not prove firm supply or compliance at a named site. Excluded from operating-capacity totals and scores.The Star report of a written parliamentary reply source ↗
- ST Telemedia Global Data CentresPlanned · Accepted
Johor · Evidence 13 Aug 2026
Development pipeline capacity ceiling. STT Johor is planned for up to 166 MW of IT load. The normalized 166 MW value is an explicit publisher-reported upper bound for one named campus, not exact pipeline capacity, operating capacity or a Malaysia market total.STTGDC Johor financing release source ↗ - TM Nxera Iskandar Puteri CampusPower agreement · delivery unverified · Accepted
Johor · Evidence 12 Jan 2026
Secured or contracted power. TM reports a signed multi-year electricity supply agreement with TNB securing 280 MW for its named Iskandar Puteri campus. The agreement is contracted power, not evidence that 280 MW is energised or currently delivered. The first-phase 2026 operations target was forward-looking; no energisation date, curtailment terms, IT-load basis, or current operational status was verified.TM Nxera Johor electricity supply agreement 2026 source ↗
11 other proposals concern policy, demand, grid load, investment or broader market context.